North Port Oval works


From the Port Philip Leader
Reported by Paul Riordan
Full Article

THE $4.7 million redevelopment of Port Melbourne’s North Port Oval was delayed after tests revealed the playing surface was contaminated.

But Port Phillip Council said the work was “now back on track” because the results posed no future threat to users or the building project.

Port Melbourne Football Club director Peter Bromley said the club “would have liked to have seen the work start faster”.

“Contamination is a nuisance, but a considerable part of Port Melbourne has contamination issues so it’s not surprising.

“It’s prudent to do these tests first ,” Mr Bromley said.

He said the last upgrade at the Williamstown Rd ground was in 1946 when the American army left behind US$20,000 after using it as a base during World War II.

The council is expected to appoint an architect for the project this month.

The State Government has chipped in $1 million for the project, Port Phillip Council will pay $1.7 million and Football Victoria $500,000. The balance will be paid by the football club.

A community reference group will be set up this month, with the council expected to ask interested people to join.

NorthPort Sun, 23 Aug 2009 - 08:58

Good news that there will finally be some action underway. For the future of thclub it's important that these works go ahead. I can't see facilities from 80 years ago really appealing to the mid-20s to 30-year old newer population of Port Melbourne.

Hopefully night lighting is next on the agenda.

Paul Amy's recent piece on the dwindling crowd numbers at Port Melbourne is a massive concern, especially with the number of new residents moving into the area. The club must try new things to engage that potential supporter base.

Talk at the ground yesterday was that Ingles St side of the ground may be left undeveloped, a new building will replace the area between the Norm Goss Stand, and the older Wooden stand down at what these days is called the Bolte Bridge end.

If the club could have a facility capable of running as a sports bar/club midweek, they may be a chance chance of attracting new people to the club. Especially if Port look at night footy.

If the council meetings are open to the public, I'd be interested in going along.

NorthPort Wed, 9 Sep 2009 - 20:09

Any news on the renovations? We are less than a month from the October cut-off date.

NorthPort Thu, 24 Sep 2009 - 17:16

Answering my own post, but we should see action in April 2010. If the building is on the Norm Goss Stand wing, perhaps the land behind might be a possible acquisition for the renovation.

NorthPort Mon, 28 Sep 2009 - 00:27

http://www.portphillip.vic.gov.au/default/Provision_of_Architectural_Se…

Table of Contents – Specification
1. INTRODUCTION 54
2. BACKGROUND 54
3. OBJECTIVES OF PROJECT 55
4. DESIGN REQUIREMENTS 55
5. PROJECT BRIEF 56
6. CLIENT 56
7. LEVEL OF SERVICE 57
8. PROJECT GOVERNANCE 57
9. SCOPE OF SERVICES 58
10. PHASES OF CONSULTANCY WORK 58
11. CONSULTATION 59
12. INFORMATION AVAILABLE TO APPOINTED CONSULTANT 59
13. INSPECTION OF SITE 60
14. PROJECT MILESTONES 60
15. MEETINGS 60
16. REPORTING 61
17. DELIVERABLES 61
18. PERMITS AND APPROVALS 61
19. ENGAGEMENT OF SUB CONSULTANTS 62
20. FEE PROPOSAL 62
21. PAYMENT SCHEDULE 62
22. EVALUATION AND SELECTION CRITERIA 63
Specification
1. INTRODUCTION
Port Melbourne Cricket Ground is located on the corner Williamstown Road and Ingles Street in Port Melbourne, approximately 2.5 km from the Melbourne CBD. Established in 1886 the ground has played an important role in establishing the identity of Port Melbourne by hosting a range of sport and cultural activities over many years.
As the Committee of Management for the reserve, the Port Phillip City Council recognises the role of the Port Melbourne Cricket Ground as a venue for both elite and community level activities, with strong historical and cultural links to the evolution of sports in the Port Melbourne region.
2. BACKGROUND
The Port Melbourne Cricket Ground is a reserve under the Crown Lands Act with the Port Phillip City Council designated as the Committee of Management. Occupation of the site is managed through seasonal crown licences with the Port Melbourne Football Club and Port Melbourne Cricket Club.
The Port Melbourne Football Club (PMFC) has used Port Melbourne Cricket Ground as its training and administration base since 1886 and has hosted a number of historical VFA and VFL matches. The Port Melbourne Cricket Club (PMCC) has also been located on the site since 1874 and is one of the eight original competing teams with the Victorian Sub district Cricket Association.
With the exception of the playing surface, since circa 1940 little has been spent on maintenance of the facilities and grandstands, resulting in many of the facilities being in a state of disrepair. This, combined with a lack of capital expenditure for modernisation, has allowed the venue to decay to its present unacceptable condition.
Football Victoria, Port Melbourne Football Club and the City of Port Phillip City Council have a joint desire to see the existing facilities refurbished / upgraded. To this end the parties commissioned the preparation of a project feasibility review for the future development of the Port Melbourne Cricket Ground to accommodate the objectives of the key stakeholders of the site.
In an area experiencing rapid changes in socio-economic and demographic characteristics, the venue affords both a tangible link to local history and an opportunity for delivery of a wide range of sports and recreational services to the community
Council’s priorities for the venue relate to cultural, environmental, economic and social equity objectives as articulated in the City of Port Phillip Plan. The key outcomes of the proposed redevelopment are for a facility that is fit for purpose; opportunities to increase participation relevant to the venue; and provide an opportunity for Port Melbourne Football Club to reconnect with the Port Melbourne Community.
3. OBJECTIVES OF PROJECT
The project objective is the redevelopment of the football club facilities at the North Port Oval, to be jointly funded by the City of Port Phillip, Sport & Recreation Victoria, Australian Football League and the Port Melbourne Football Club. Football Victoria has identified Port Melbourne Cricket Ground as a strategic asset for its operations due to its central location and acknowledges the upgrading of the venue as a facility that can continue to meet the needs of Port Melbourne Football Club and the VFL.
The proposal is to redevelop a combination of high quality training and administrative facilities for the Club as well as a range of multifunctional community focused facilities. This redevelopment will ensure the club has the standard of facilities required for the elite level sporting club as well as providing much needed community facilities to create a key activity hub in the precinct.
The initial phases of the project must review and establish the most effective location for the redevelopment taking into account the sites existing facilities and limitations to deliver the most efficient outcome in line stakeholders objectives. One of the key challenges in this project will be the management of the existing facilities and opportunities to improve the general landscape and access. Of particular interest is the inclusion of the existing grandstand (the Goss Stand) to ensure this iconic structure is managed and maintained for the future.
4. DESIGN REQUIREMENTS
4.1 Environmental Sustainable Design
It is essential that an underlying principle of the redevelopment be to utilise an environmentally sustainable design philosophy in a holistic manner as well as in detail for energy and water usage. It is expected that leading edge ESD design principals will be incorporated into the design with the objective to achieve at least 5 Stars under the Green Star rating tool for public buildings, as produced by the Green Building Council of Australia (GBCA).
4.1 Landscape
It is essential that consideration be given to the landscape design with a view to improving both the perception and use of the facility and grounds by the broader / general public.
4.2 Heritage
It is essential that the heritage fabric of North Port Oval, and in particular the Grandstand be well understood and sympathetically treated in any redevelopment of the grounds and buildings and in the renewal of the Goss Grandstand itself.
4.3 General design requirements include:
Practicality of designs.
Flexibility for usable space.
Sensitivity to resident opinion and local community requirements.
Security & Safety
Fire Safety Systems
Voice and data systems
Car parking and access
Susceptibility to Vandalism and Graffiti
Maintenance and cleansing ability (i.e. minimum maintenance)
Aesthetics & Urban design
Use of Recycled materials
Natural and artificial lighting
Functional design to ensure a “user friendly” environment that is” fit for purpose “.
Long term operational costs and maintenance requirements
Energy efficiency and Environmental Sustainable design practices.
Compliance with relevant all Australian Standards
Compliance with Building Code of Australia
Compliance with DDA requirements
Access and Egress
Staff and Public Amenity
5 PROJECT BUDGET
The overall estimated capital construction budget for this project is set to a maximum of A$ 4.7 million dollars. This figure is structured on provisional capital contributions through satisfactory obtainment of all stakeholders’ objectives through the initial phases of the project.
The key contributors to the project are: The City of Port Phillip, Sports & Recreation Victoria, The Port Melbourne Football Club and the Australian Football League.
This budget allocation includes:
• All design consultants and sub consultants fees
• Design, documentation and specifications
• All permits , fees and changes
• Construction costs.
• Project Contingencies and Administration
• Defect Control and Management
6 CLIENT
A client group, the Project Control group (PCG) has been established and comprises representatives from the City Of Port Phillip, Sports & Recreation Victoria, The Port Melbourne Football Club and the AFL. The Principal for this commission will be the Port Phillip City Council.
7 LEVEL OF SERVICE
The Principal and other stakeholders require the highest standard of design, coordination and quality assurance during the project to ensure a high quality project is produced on time and within budget. Should works exceed the budget specified above, the Consultant shall amend the drawings to bring costs within budget at no further expense to the Principal or stakeholders.
8 PROJECT GOVERNANCE
8.1 Project Agreement
It is proposed that the City of Port Phillip, AFL, Sports & Recreation and The Port Melbourne Football Club will enter into a joint funding and administrative agreement. This agreement will reinforce the project governance processes and structure.
8.2 Project Control Group
The Project Control Group will provide overall direction of the project. The group is a core group to direct, guide facilitate and approve development and delivery to ensure that the key objectives are successfully delivered.
8.3 Project Working Group
The Project Working Group is to deliver the functional and operational input and decisions required to deliver the project. The group is the key operational link that will inform and guild the consultancy team to deliver a fit for purpose facility in line with user’s expectations.
8.4 Project Manager
The Project Manager will be responsible for:
• Management of the project team
• Design and documentation process
• Management of the construction budget
• Management of the project schedule & timelines
• Appointment of Superintendent under the General Condition of Contract
• Project delivery strategy
• Tender & contract documentation preparation
• Tender assessment and awarding of contracts
• Project management, construction and contract administration
8.5 Architect
The Architect is responsible for the services as described in this brief.
The architect will be the principal consultant for this project and is responsible for the coordination of the design consultants and the development of the schematic design.
9 SCOPE OF SERVICES
All architectural and associated services will be undertaken in accordance the objectives outlined in this project brief.
The tenderer shall read this brief in full, familiarise themselves with the site and all existing information relating to the project and submit within the time specified time a tender submission and fee proposal in accordance with this brief. The Architect shall be responsible for engaging his/her own sub-consultants to provide a wide range of expertise to the project.
The Architect shall be fully responsible for designing works to meet the projects budget and shall provide fully estimated cost plans by a registered quantity surveyor as required.
10 PHASES OF CONSULTANCY WORK
To facilitate the delivery of this complex project and accommodate all stakeholders objectives the architectural consultancy will be delivered in phases as outlined in this project brief.
The engagement is to undertake all phases outlined in this brief, however the ongoing engagement for phase 3 & 4 is subject to council’s ongoing financial commitment to this project. As such the initial works will be limited phase 1 (pre design) and phase 2 (Schematic design) at this time pending council’s commitment to funding of the project in the 2010/2011 financial year.
The initial consultancy commission will include but is not limited to:
Phase 1: Pre- Design
10.1 Review of existing reports & documentation.
10.2 Site Investigation of existing facilities.
10.3 Interviews with all key stakeholders & PCG.
10.4 Conformation of positioning options for development
10.5 Authority Requirements, planning, Heritage, traffic reports etc
10.6 Development of Functional & Technical Brief (FTB).
10.7 Pre Design Summary Report & Program. (Presentation)
Phase 2: Schematic Design
10.8 Development of ESD objectives
10.9 Development of concept design option (A)
10.10 Development of Cost Plan (A)
10.11 Development of Estimated Lifecycle Management Plan (15 year)
10.12 Design Development Report & Updated Program (Presentation)
Possible subsequent phases of the consultancy may include but is not limited to:
Phase 3: Design Development & Documentation
10.13 Conformation of design
10.14 Detailed design
10.15 Detailed Cost plan (B)
10.16 Tender Documentation & Specification
10.17 Final Design Report & Delivery Program
Phase 4: Tendering & Construction Management
10.18 Tender Analysis, Evaluation & Reporting
10.19 Construction Supervision and Contract Administration
10.20 Defects Liability Supervision and Administration
11 CONSULTATION
11.1 Community Consultation
Council will coordinate and manage any and all consultation with the community. The successful consultant will be expected to attend meetings as requested and be reimbursed in accordance with tendered schedule of rates.
11.2 External Consultation - (stakeholders)
The consultant will be required to consult with all the relevant external stakeholders through the allocated meetings structure and reporting requirements.
11.3 Internal Consultation
The consultant will be required to consult with all the relevant council officers and councillors in order to accurately and properly complete initial phases of this project.
Internal consultation will include but not limited to:
• Councillors
• CEO and Executive Team
• Client Manager
12 INFORMATION AVAILABLE AS PART OF THE PROJECT. (TO BE MADE AVAILABLE ON APPOINTMENT OF CONSULTANT)
12.1 Previous studies, reports and data

NorthPort Mon, 28 Sep 2009 - 00:36

Council papers from August meeting:
http://www.portphillip.vic.gov.au/default/A10_-_North_Port_Oval_Consult…

AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
42
STRATEGY AND POLICY REVIEW COMMITTEE
4 AUGUST 2008 POLICY AND PLANNING
A5 PROPOSED RE-DEVELOPMENT OF
NORTH PORT OVAL (AKA PORT
MELBOURNE CRICKET GROUND)
LOCATION/ADDRESS: INGLES ST AND WILLIAMSTOWN RD,
PORT MELBOURNE
RESPONSIBLE EXECUTIVE DIRECTOR: GEOFF OULTON EXECUTIVE DIRECTOR
COMMUNITY DEVELOPMENT AND
PLANNING
AUTHOR: FIONA BLAIR, YOUTH AND
RECREATION CO-ORDINATOR
IAN HICKS, MANAGER CULTURE AND
RECREATION
FILE NO.:
ATTACHMENTS: LETTER OF PORT MELBOURNE
FOOTBALL CLUB (DATED 8 JUNE 2005)
LETTER OF CITY OF PORT PHILLIP
(DATED 17 SEPTEMBER 2007)
1. EXECUTIVE SUMMARY
1.1. Council’s 2007 Sport and Recreation Strategy aims within 4 years to:
• increase participation in sport and recreation by 10%
• ensure all sports facilities are 100% fit for purpose.
1.2. Council’s Sport and Recreation Guidelines identify Councils hierarchy of
investment in sport, which proportionally encourages greater investment
from Council in community (‘grass roots’) sports and facilities. Councils level
of investment is proportionally decreased where facilities are utilized at a
more elite level of sports and are more exclusively used for elite level sport.
1.3. During 2005/06 a draft Masterplan was developed for North Port Oval. This
was prepared at the request of Football Victoria and included Port
Melbourne Cricket club and City of Port Phillip, being Committee of
Management for the site. The interest of Football Victoria at this time was to
prepare a document that would look at the future needs of North Port Oval
and position the facility as part of a package of facilities being put to
Government for consideration.
1.4. In May 2008 it was announced that the State Government was to contribute
$1M to the re-development of North Port Oval as part of a series of VFL
venue refurbishments and re-developments.
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
43
1.5. The funds available for redevelopment of North Port Oval include:
• $1M Department of Sport and Recreation (State Government)
• $500K Football Victoria
• $1.5M Port Melbourne Football Club
1.6. This report recommends that Council agree ‘in-principle’ to contribute $1.7M
(for a total project of $4.7M) to achieve a range of community benefits that
would result from the redevelopment of North Port Oval.
2. BACKGROUND AND CONTEXT
2.1. In 2005 Council was requested by Port Melbourne Football Club and
Football Victoria to part fund the preparation of plans for the redevelopment
of North Port Oval based on achieving a series of objectives (refer to
attachment 1).
2.2. In 2006 the working group drafted a ‘North Port Oval Redevelopment
masterplan’. Council has not formally adopted this masterplan and it is not
recommended that Council do so at this time.
The purpose of the masterplan was to indicate a potential scope of works for
North Port Oval, and for it to be used as a ‘positioning’ paper by Football
Victoria in its quest to obtain funding for the redevelopment of North Port
Oval.
Now that a budget has been identified its is more appropriate that the draft
masterplan be used as an input into a design and feasibility study that will
determine a new plan, within a known budget to deliver clear and agreed
community benefits.
2.3. In September 2007, the Port Melbourne Football Club and Football Victoria
indicated to City of Port Phillip that a bid for funds to complete works on a
number of ‘VFL’ venues was to be presented to Government.
2.4. On 25 September 2007, the City of Port Phillip provided ‘in-principle’ support
to making a significant financial contribution for the project subject to
ratification by Council (refer to attachment 2).
2.5. In May 2008 the Government announced capital funding for a number of
‘VFL’ venues, including $1M toward the redevelopment of North Port Oval.
2.6. On 6 June 2008 the City of Port Phillip affirmed ‘in principle’ support for the
project at $1.7M subject to Council ratification.
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
44
3. RECOMMENDED OPTION
Council agrees ‘in-principle’ to commit $1.7M to achieving the community
benefits outlined in this report resulting from the redevelopment of North Port
Oval.
3.1. Criterion for recommendation
3.1.1. Council’s investment is consistent with Council Policy –
specifically the ‘Sport Strategy’ and City of Port Phillip’s
‘Sport and Recreation Guidelines’.
The Council’s investment will be consistent with Council’s Sport
Strategy and Guidelines with regard to:
• all Council sporting facilities being ‘fit for purpose’ within
the next 4 years;
• consistency with Council’s financial principles and
approach for investment in sport and recreation facilities
(as outlined in Council’s Sport and Recreation Strategy
Guidelines adopted November 2007).
• Consistency with Council’s Open Space Strategy 2006
• City of Port Phillip maintains land manager status for
North Port Oval
3.1.2. Council’s investment minimises risk and increases
compliance with Council statutory obligations associated
with public venues, as applicable.
The risks and statutory compliance issues to be minimised
through the redevelopment of North Port Oval including:
• Rectification of any structural/ building integrity issues
where there is a identified risk to user and / or public
safety;
• Improvements in the environmental performance of the
venue, consistent with Council policy.
3.1.3. Council contribution delivers value for money and a
demonstrable benefit to the community.
The demonstrable community benefits to be delivered by the
redevelopment of North Port Oval include:
• Renewal of the Gross Grandstand and retention of it’s
heritage values;
• Provide for the future sustainability of both Port
Melbourne Football Club and Port Melbourne Cricket
Club.
• Develop and improve Club rooms and player change
facilities in a manner consistent with the AFL Preferred
Facilities Guidelines 2006;
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
45
• Increase use and accessibility by the public through
improving both visual and physical permeability from the
public realm into the venue, thereby increasing the
attractiveness of the reserve as a public open space;
• Increase access to the facilities and expand the services
at the ground for example by providing infrastructure that
encourages greater use of the venue by the community
and increased physical activity opportunities (eg:
consideration to a playground facility, consideration for
use by athletics and/or local schools etc).
• Promote connection and exchange between the Club and
the existing local community for example increasing
opportunities for residents to meet and interact at the
ground and in club activities
3.2. Sustainability assessment
Economic
Pillar
North Port Oval is the responsibility of the City of Port
Phillip in it’s role as Committee of Management under the
Crown Land Reserves Act 1979.
The recommended option would provide for an investment
of $1.7M from CoPP toward a $4.7M redevelopment of
North Port Oval – being 40% of the anticipated total project
investment / cost.
The potential to also reduce Council’s ongoing and yearly
maintenance costs for the venue will be investigated as
part of this project.
Environmental
Pillar
The redevelopment of North Port Oval will provide an
opportunity to improve the environmental performance of
the existing facilities through the application of Council’s
Environmentally Sustainable Design (ESD) principles and
policies.
Although the application of ESD may have some
limitations, with most of the current facilities dating between
40 and 80 years in age, significant improvements in
environmental performance would be anticipated.
Cultural
Pillar
North Port Oval has been utilized as a sporting facility for
137 years. The venue has a deep cultural heritage as the
home to Port Melbourne Cricket Club for 137 years and
home to the Port Melbourne Football Club for 123 years.
The venue also retains the Norm Goss Grandstand, which
not only acts a facility for viewing but also retains some
heritage importance to the local community.
The redevelopment of North Port Oval will ensure that it’s
use as a major sporting facility and the retention of the
heritage values of the Norm Goss grandstand are retained.
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
46
Social
Pillar
The project is intended to improve connections between
the facility and the public realm, particularly vehicular
access and visual permeability.
The project also aims to increase the level of general public
use of the facility through the incorporation of additional
functions and activities, which may include incorporation of
a public playground.
3.3. Policy and legislative implications
This alternative position is likely to be deemed consistent with Council’s
stated policy position in the Sport Strategy 2007.
3.4. Risk implications
There is an outstanding backlog of works maintenance on facilities at North
Port Oval. This option would deal as a matter of priority through the
rectification of identified risks associated with various building structures
within North Port Oval.
3.5. Resource implications
The resource implications that ‘in-principle’ Council would contribute $1.7M
to the renewal of North Port Oval and the delivery of a range of community
benefits.
Council in the City of Port Phillip Strategic Resource Plan that was adopted
as part of the 2008/09 Budget process has identified $200,000 in 2008/09
and $1.5M in 2010/11 for redevelopment of North Port Oval.
4. ALTERNATIVE OPTIONS
4.1. Alternative 1
Council reduce the scope of the works to community benefit and
commensurately reduce the level of ‘in-principle’ financial support.
4.1.1. Sustainability assessment
Economic
Pillar
As a priority Council would be advised (under this
alternative) to undertake the ‘backlog’ maintenance works
as a mater of priority. These works are currently estimated
at $600,000.
Under this option it is likely that the State Government’s
contribution of $1M would be withdrawn.
However, Council may still wish to invest in a much more
limited scope of community benefit, the scope of which
would need to be determined dependant on the level of
financial support Council was wishing to contribute.
Environmental
Pillar
The environmental performance of the facilities at North
Port Oval will retain the status quo and are unlikely to
undergo any significant improvement.
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
47
Cultural
Pillar
The facility in the short to medium term is likely to be able
to continue to be utilized for football and cricket.
Notwithstanding this, there is currently some concerns
raised by officials attending matches at North Port Oval
with regard to the ‘fitness of this facilities to service their
purpose *(eg: umpire change facilities for men and
women).
Social
Pillar
The objectives of Councils own Sport Strategy, specifically
with regard to ensuring all Council facilities are ‘fit for
‘purpose’ would be compromised. It is the authors/officers
view that at present the facilities at North Port Oval are not
of a standard that would deem them fit for purpose.
4.1.2. Policy and legislative implications
This alternative position is likely to be deemed inconsistent with
Council’s stated policy position in the Sport Strategy 2007.
4.1.3. Risk implications
There is an outstanding backlog of works maintenance on
facilities at North Port Oval. Also, some preliminary structural
assessments indicate that there are a number of aged facilities
and buildings at North Port Oval that require remediation works
in the short to medium term to obviate potential risks to public
safety should these facilities continue to deteriorate.
4.1.4. Resource implications
The resource implications of this alternative are that the
rectification and remediation works would still be required.
These works are currently estimated at $600,000.
4.2. Alternative 2
Council seek to just minimize risk and meet statutory obligations, while not
endeavoring to gain any broader community benefit from the North Port
Redevelopment.
4.2.1. Sustainability assessment
Economic
Pillar
Council will still retain a ‘backlog’ of maintenance works
currently estimated at $600K that is required to be
completed at North Port Oval to address risk and statutory
obligations.
Under this alternative the State Government is very likely to
withdraw is $1M of funds towards the North Port Oval
redevelopment.
Environmental
Pillar
The environmental performance of the facilities at North
Port Oval will retain the status quo and not undergo any
improvement.
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
48
Cultural
Pillar
The facility on the short to medium term is likely to be able
to continue to be utilized for football and cricket.
Notwithstanding this, there is currently some concerns
raised by officials attending matches at North Port Oval
with regard to the ‘fitness of this facilities to service their
purpose *(eg: umpire change facilities for men and
women).
Social
Pillar
The objectives of Councils own Sport Strategy 2007,
specifically with regard to ensuring all Council facilities are
‘fit for ‘purpose’ would be compromised. It is the
authors/officers view that at present the facilities at North
Port Oval are not of a standard that would deem them fit for
purpose.
The level of obvious community benefit to be derived from
Council’s $600,000 investment will be limited. The
objectives of improved access, increased use and
improved environmental performance would not be
achieved.
4.2.2. Policy and legislative implications
This alternative position is likely to be deemed inconsistent with
Council’s stated policy position in the Sport Strategy 2007.
4.2.3. Risk implications
There is an outstanding backlog of works maintenance on
facilities at North Port Oval. Also, some preliminary structural
assessments indicate that there is a number of aged facilities
and buildings at North Port Oval that require remediation works
in the short to medium term to obviate potential risks to public
safety should these facilities continue to deteriorate.
There is a potential risk to public safety should the rectification
and repair of these structures not be attended to as would be the
case under this alternative option.
4.2.4. Resource implications
The resource implications of this alternative are that the
rectification and remediation works would be outstanding and
remain uncompleted. These works are currently estimated at
$600,000.
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
49
5. PARTICIPATION AND ENGAGEMENT
5.1. Internal
5.1.1. The people who will be engaged with in relation to this issue are:
• Kathy Dillon – Manager Asset Management
• Chris White – Co-ordinator Open Space
• Sam Hewett – Manager Capital Works
5.2. External
5.2.1. The external people and/or organisations who have and will
continue to be engaged in relation to this issue are:
• Sport and Recreation Victoria
• Port Melbourne Football Club representatives
• Port Melbourne Cricket club representatives
• Football Victoria representatives
5.2.2. A North Port Redevelopment Working Group has been
established and includes membership from Sport and Recreation
Victoria, Port Melbourne Football Club, Football Victoria and City
of Port Phillip.
6. IMPLEMENTATION
6.1. Stage one of the Project Plan will be implemented including:
6.1.1. A Working Group comprising of City of Port Phillip, the Port
Melbourne Football Club, Football Victoria and Sport and
Recreation Victoria has been established.
6.1.2. A consultant has been appointed to undertake the design and
feasibility study that will identify the scope of project and the
community benefits to be derived within the total budget
allocated for construction (approximately $4.7M).
6.1.3. A Report will be prepared for Council’s consideration at the
conclusion of the design and feasibility study for Council to
determine whether the criteria underpinning Council’s ‘inprinciple’
financial support have been met.
7. COMMUNICATION
7.1. Dependant on Council’s resolution, it is intended that a community project /
information board will be placed on site to both inform and seek feedback
from the community, with particular regard to the community benefit
elements of the project.
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
50
8. RECOMMENDATION
That the Strategy and Policy Review Committee recommend that Council resolve:
8.1. That the Council resolve to support ‘in-principle’ the redevelopment of North
Port Oval with a commitment of $1.7M.
8.2. That the Council’s ‘in-principle’ commitment assumes that a range of
community benefits and objectives will be achieved, including:
8.2.1. Consistency with Council Policy – particularly the ‘Sport Strategy’
and City of Port Phillip’s ‘Sport and Recreation Strategy
Guidelines’ (adopted November 2007) with specific regard to:
• Council sporting facilities being ‘fit for purpose’ within the
next 4 years;
• consistency with Council’s financial principles and
approach for investment in sport and recreation facilities
(as outlined in Council’s Sport and Recreation Strategy
Guidelines);
• consistency with Council’s Open Space Strategy 2006;
• consistency with Memorandum of Understanding
between City of Port Phillip and Sport and Recreation
Victoria;
• City of Port Phillip maintaining public land manager status
for North Port Oval.
8.2.2. Minimisation of risk and increased compliance with statutory
obligations associated with public venues, as applicable,
including:
• Rectification of any structural/ building integrity issues
where there is a identified risk to user and / or public
safety;
• Improvements in the environmental performance of the
venue, consistent with Council policy.
8.2.3. Deliver value for money and a demonstrable benefit to the
community, including:
• Renewal of the Goss Grandstand and retention of it’s
heritage values;
• Provide for the future sustainability of both Port
Melbourne Football Club and Port Melbourne Cricket
Club.
• Develop and improve Club rooms and player change
facilities in a manner consistent with the AFL Preferred
Facilities Guidelines 2006;
• Increase use and accessibility by the public through
improving both visual and physical permeability from the
public realm into the venue, thereby increasing the
attractiveness of the reserve as a public open space;
AGENDA - STRATEGY AND POLICY REVIEW COMMITTEE - 4 AUGUST 2008
51
• Increase access to the facilities and expand the services
at the ground for example by providing infrastructure that
encourages greater use of the venue by the community
and increased physical activity opportunities (eg:
consideration to a playground facility, consideration for
use by athletics and/or local schools etc).
• Promote connection and exchange between the Club and
the existing local community by increasing opportunities
for residents to meet and interact at the ground and in
club activities
8.3. That Council seek a further report for its consideration at the conclusion of
the design and feasibility study in order for Council to determine whether the
community benefits and objectives outlined in 8.2 (above) have been met,
with a view to confirming the level of financial support to be provided for the
redevelopment of North Port Oval.

digs Mon, 28 Sep 2009 - 09:26

zebraman wrote:is this the longest single post on record??

More to the point, Did anyone read it?

Dolphin Mon, 28 Sep 2009 - 11:40

Dale61 wrote:

zebraman wrote:is this the longest single post on record??

If it was all entered manually, then possibly yes, but my guess is it is a cut-and-paste, which would then be no as I've seen (and deleted) longer.

Spinner